Easily Pass 70-178 Exam By Training Lead2pass New Microsoft Practice Materials VCE Dumps (51-60)

If you want to prepare for 70-178 exam in shortest possible time, with minimum effort but for most effective result, you can use Lead2pass 70-178 Practice Test which simulates the actual testing environment and allows you to focus on various sections of 70-178 Exam. Our candidates walk into the testing Room as confident as a Certification Administrator. So you can pass the eaxm without any question.

QUESTION 51
You manage a project that specifies all constraint types to As Soon As Possible.
You discover that one of your key tasks is scheduled to end prior to the targeted finish date.

You need to display the targeted finish date on the default Gantt chart.
What should you modify in the Task Information window?

A.    Set the Deadline date field.
B.    Set the Constraint date field.
C.    Set the Finish date field.
D.    Select the Mark task as milestone check box.
E.    Select the Display on Timeline check box.

Answer: A

QUESTION 52
The first major phase of your project is scheduled for a duration of 45 days.
However, you do not have task information for other phases.
You need to indicate that the duration of the entire project is 200 days.
What should you do?

A.    Select the Project Summary Task option.
B.    Select the Summary Tasks option.
C.    Create a manually scheduled summary task.
D.    Update the project calendar.

Answer: C

QUESTION 53
The project you manage has only part-time resources.
The part-time resources work four hours a day from Wednesday through Saturday.
You need to create a new calendar and set the calendar as the default for your project.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

A.    Select the part-time calendar from the Change Working Time window.
B.    Set the calendar type to part-time for all tasks.
C.    Select the part-time calendar from the Project Information window.
D.    On the Project tab, Select Change Working Time, and then click Create New Calendar.
E.    Change the Calendar type in the Project Options dialog box.

Answer: CD

QUESTION 54
You need to set the default constraint type for all new tasks to As Late As Possible.
What should you do?

A.    Select all tasks, and then click Layout.
B.    In the Options dialog box, enable the New Tasks are effort driven check box.
C.    Select all tasks, and then set the constraint type to As Late As Possible.
D.    In the Project Information window, from the Schedule From drop-down list box, select Project Finish Date.

Answer: D

QUESTION 55
You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit button.)

image_thumb

You need to set the Task Mode for task 4 to be the same as task 6.
What should you do?

A.    Create a task dependency from Task 4 to Task 6.
B.    Set Task 4 as critical.
C.    Add a 1 day lead to Task 4.
D.    Set Task 4 as manually scheduled.

Answer: D

QUESTION 56
You use bottom-up scheduling.
You need to group four consecutive tasks in a major phase.
You highlight the four tasks.
Which command should you use?

A.    Outdent
B.    Fill Down
C.    Insert Summary
D.    Move Task

Answer: C

QUESTION 57
Drag and Drop Question
You use Microsoft Project Professional 2010 to manage an engineering project according to the schedule as shown in the exhibit. (Click the Exhibit button.)
Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on the first day and informed you that he needs an additional 9 hours of work to finish.
You update the schedule.
What percentage of units should be reflected in the schedule by Adam’s workload? (To answer, drag the appropriate units to the correct locations in the answer area.)

image_thumb[1]

Answer:

image_thumb[2]

QUESTION 58
You need to ensure that you can view only the tasks on your projects critical path.
What should you do?

A.    On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box.
B.    View the projects Gantt chart and apply the Critical group.
C.    View the project’s Gantt chart and apply the Critical filter.
D.    On the Advanced tab of the Project 2010 options, modify the Tasks are critical if slack is less than or equal to option.

Answer: C

QUESTION 59
The red person icon is displayed next to one of your tasks.
You need to find out the reason for the display of the icon.
What should you do?

A.    Display the task details.
B.    Use the Level Resource feature.
C.    Use the Task Inspector tool.
D.    View the task information.

Answer: C

QUESTION 60
One of your tasks in your project plan is 50 percent complete.
The task has a finish variance of 4 days and a work variance of -14 days.
Which set of values describes the task?

A.    The task is early by 14 days.
B.    The task is early by 4 days.
C.    The task is late by 4 days.
D.    The task is late by 14 days.

Answer: C

If you want to get more 70-178 exam preparation material,you can download the free demos in PDF files on Lead2pass.It would be great help for you exam.Wish you pass the exam successfully.

www.lead2pass.com/70-178.html